Which role is responsible for ensuring that a project or programme of change meets its objectives?

Prepare for the BCS Foundation Certificate in Business Change. Study with multiple choice questions and in-depth explanations. Get exam ready!

Multiple Choice

Which role is responsible for ensuring that a project or programme of change meets its objectives?

Explanation:
The Senior Responsible Owner (SRO) plays a crucial role in ensuring that a project or programme of change meets its objectives. This individual is typically appointed at the outset of the initiative and carries the overall accountability for the success of the project or programme. The SRO is responsible for strategic oversight, ensuring alignment with organizational goals, and maintaining stakeholder engagement throughout the process. By having a clear focus on the objectives, the SRO can make informed decisions, allocate resources effectively, and resolve issues that may arise during the project. This position acts as a bridge between the project team and higher management, ensuring that the vision is effectively communicated and that the project maintains its direction toward achieving the desired outcomes. The emphasis on accountability and strategic alignment underscores the importance of the SRO in driving the project towards success.

The Senior Responsible Owner (SRO) plays a crucial role in ensuring that a project or programme of change meets its objectives. This individual is typically appointed at the outset of the initiative and carries the overall accountability for the success of the project or programme. The SRO is responsible for strategic oversight, ensuring alignment with organizational goals, and maintaining stakeholder engagement throughout the process.

By having a clear focus on the objectives, the SRO can make informed decisions, allocate resources effectively, and resolve issues that may arise during the project. This position acts as a bridge between the project team and higher management, ensuring that the vision is effectively communicated and that the project maintains its direction toward achieving the desired outcomes. The emphasis on accountability and strategic alignment underscores the importance of the SRO in driving the project towards success.